In partnership with our main contractor ES Moss, the JHP team undertook a comprehensive Electrical Distribution Upgrade and Internal Refurbishments of NHS Trust Care Home, Elizabeth Court’s ensuite bathrooms.
Along with a transformative refurbishment that enhances the overall functionality and aesthetics of the facilities, the Care Home now boasts a state-of-the-art electrical distribution system, aligning seamlessly with industry standards and regulations.
Background Information
We are thrilled to share the success story of our recent venture at Elizabeth Court, where we undertook a comprehensive Electrical Distribution Upgrade and Internal Refurbishments. This project, commissioned by the Hertfordshire Partnership University NHS Foundation Trust and executed through our main contractor, ES Moss Ltd, exemplifies our commitment to delivering meaningful, high-quality installations.
Project Overview:
Elizabeth Court. Electrical Distribution Upgrade & Internal Refurbishments.
Client : Hertfordshire Partnership University NHS Foundation Trust Duration : August 2023 – January 2024
Addressing Challenges with Innovative Solutions:
Our journey began with the client’s pressing need to replace an outdated electrical distribution system and renovate the en-suites. A vacant NHS facility with years of dormancy presented unique challenges, including careful coordination with other construction works. Swiftly adopting innovative solutions, we meticulously programmed isolations to minimize disruptions, ensuring a seamless workflow around ongoing activity.
Strategic Approach:
Our methodology involved installing temporary power supplies for critical circuits, such as fire alarms and data cabinets, to facilitate uninterrupted progress. Stripping out the old cabling and distribution boards, we embarked on installing new Low Smoke (LSF) sub-mains cabling, MCCB panel boards, and distribution boards, all compliant with the latest regulations. Thorough testing and identification of existing installation faults allowed us to rectify and upgrade as necessary.
Results and Achievements:
Upon project completion, Elizabeth Court now boasts a state-of-the-art electrical distribution system, aligning seamlessly with industry standards and regulations. The en-suites underwent a transformative refurbishment, enhancing the overall functionality and aesthetics of the facility.
Client Satisfaction:
The success of this project is not only measured by the technical milestones achieved but also by the satisfaction of our esteemed client. Hertfordshire Partnership University NHS Foundation Trust now benefits from a facility that meets modern standards, ensuring safety, efficiency, and compliance with the latest regulations.
Conclusion:
In summary, our team, alongside our valued partners, has delivered on the promise of a technologically advanced and aesthetically pleasing environment at Elizabeth Court.
This case study stands as a testament to our dedication to excellence in electrical solutions.